Three-Week Look Ahead Schedule

  Week #1 Week #2 Week #3
  M T W TH F S S M T W TH F S S M T W TH F S S
  May 14             May 21             May 28            
Phase 5 -- Building CE
Install Masonry Vaneer                                          
Paint                                          
Install Ceiling Grid 1st Floor                                          
Install MEPs Finishes in Ceiling Grid                                          
Install Millwork                                          
Install VCT                                          
Install Ceramic Tile                                          
Install Fluid Applied Floor                                          
Hand Doors on First Floor                                          
Install Marker Boards, Tack Boards, Lockers                                          
Phase 5 -- Building B
 Install Overhead Rough                                          
Install Roofing                                          
Rough Walls 2nd Floor                                          
Drywall 2nd Floor                                          
Complete Masonry Interior Walls                                          
Frame Exterior Wall, Install Dense Glass                                          
Install Air Barrier on Exterior Wall                                          
Install Masonry Veneer                                          
Rough Walls 1st Floor                                          
Drywall 1st Floor                                          
Exterior Wall Repair
Install EIFS Finish Coat, B Building, North Elevation                                          
Complete Framing, B Building, South Elevation                                          
Install EIFS System, B Building, South Elevation                                          
Install EIFS Finish Coat, B Building, South Elevation