Salem School Renovation Projects: Three-Week Look Ahead

Three-Week Look Ahead Schedule

  Week #1 Week #2 Week #3
  M T W TH F S S M T W TH F S S M T W TH F S S
 

June 12

            June
19
            June
26
           
Phase 4 D Building Automotive
Punch List                                          
Owner Move Equipment in Set Up                                          
Phase 4 Building C
Install Overhead Rough                                          
Prime Paint Second Floor                                          
Masonry Veneer                                          
Install Exterior Windows                                          
Sheetrock Tape First Floor                                          
Electrical in Wall Rough First Floor                                          
Install Ceiling Grid Second Floor                                          
Install Ceramic Tile Second Floor                                          
Install MEPs Finishes in Ceiling                                          
Phase 4 D Building Woods
 Overhead Rough                                          
Prime Paint Walls                                          
Paint Overhead Steel                                          
Phase 4 Building F2
Install Finish MEPs in Grid                                          
Install Finish Flooring                                          
Install Inergen Fire System in MDF Room                                          
Install Doors and Hardware                                          
Move District Main Server to MDF                                          
Phase 5 Building A
Install Site Fencing                                          
Install Temp Walls                                          
Demo Canopy                                          
Relocate the Electric Service in Culinary